Dear investors and visitors to the site, below is the dynamics of the construction of the LCD KAMERTON as of April 2019: The device is a monolithic parking frame – 80%. Brickwork section 101 – 98%. Brickwork section 102 – 98%. Plumbing works: installation of risers for water supply, heating and fire extinguishing section 101 […]
Dear investors and visitors of the site, below is the dynamics of the construction of the Kamerton state as of December 2018: The device of the monolithic parking frame – 70%. Brickwork section 101 – 97%. Brickwork section 102 – 96% Plumbing works: installation of risers for water supply, heating and fire extinguishing section 101 […]
When buying an apartment by installments or at 100% payment – up to 25% discount on promotional apartments. The first installment is only from 20%, with the possibility of payment until December 31, 2019. The promotion is valid from 07.12.2018 to 07.01.2019 with the right of early repayment.
Dear investors and visitors of the site, below is the dynamics of the construction of the Kamerton state as of October 17, 2018: Device monolithic parking frame – 70%. Brickwork section 101 – 95%. Brickwork section 102 – 93% Plumbing works: installation of risers for water supply, heating and fire extinguishing section 101 – 95%. […]
Dear investors and visitors of the site, below is the dynamics of the construction of the Kamerton state as of September 19, 2018: Positioning of a monolithic carcass of parking – 70%. Brickwork section 101 – 95%. Brick masonry section 102 – 93% Plumbing works: installation of water supply, heating and fire suppression sections section […]
Dear investors and visitors of the site, below is the dynamics of the construction of the Kamerton state as of August 2, 2018: The device of a monolithic carcass of a parking – 70%. Brickwork section 101 – 95%. Brick masonry section 102 – 85% Plumbing: installation of risers of water supply, heating and fire […]
Dear investors and visitors of the site, we inform you that during the weekend from June 28 to July 1, the sales department will work according to the following schedule: – on June 28-30, 2006 from 10:00 to 18:00 – 01.07 from 10:00 to 17:00.
Dear investors and website visitors, the following is the dynamics of the construction of КAMERTON as of June 5, 2018: The arrangement of the monolithic frame of section №101 – 98%. Position of the monolithic frame of section №102 – 95%. The technical floor is in operation. Work has begun on the arrangement of the […]
Dear investors and visitors of the site, below is the dynamics of the construction of the Kamerton state as of May 22, 2018: The device of a monolithic frame of section № 101 – 98%. The device of a monolithic skeleton of section №102 – 95%. In the 23rd floor. Brickwork is carried out: Section […]
Dear investors and visitors of the site, below is the dynamics of the construction of the KAMERTON state on April 26, 2018: The arrangement of the monolithic frame of section №101 – 98%. Arrangement of the monolithic frame of section №102 – 90%. Works 21-22 floors. Bricklaying is carried out: section №101- in work 5-13 […]