Dynamics of construction as of March 21, 2018

Dear investors and visitors of the site, below is the dynamics of the construction of the KAMERTON state on March 21, 2018:

The device of a monolithic frame of section № 101 - 98%.
The device of a monolithic frame of section № 102 - 82%. In the 18-19th floor.
Brickwork is being carried out: Section No. 101 - in the 5-13 floors, section No. 102 - in the work of the 10-11 floor.
Plumbing works are carried out: installation of risers (101 section 83%, 102 section 57%).
The installation of window constructions is in progress: in work 4, 5, 6, 7, 8, 9 floors.
The warming of the parking was started.
Installation of ventilation and smoke removal systems is under way.