The dynamics of construction as of June 5, 2018

Dear investors and website visitors, the following is the dynamics of the construction of КAMERTON as of June 5, 2018:
The arrangement of the monolithic frame of section №101 - 98%.
Position of the monolithic frame of section №102 - 95%. The technical floor is in operation.
Work has begun on the arrangement of the carcass of the parking.
Bricklaying is carried out: section №101 - in work 12 and technical floors, section № 102 - in works 11-17 floors.
Plumbing works are carried out: installation of risers (101 sections 93%, 102 sections 85%), installation of heating systems inside apartments (2-7 floors).
The installation of window constructions is carried out: in works 9, 10, 11, 12, 13 floors.
Installation of ventilation and smoke exhaust systems is carried out.
Facade works are conducted (101 sections 50%).
Work is underway to decorate (5-9 floors).
Work is underway to set up screed in apartments (5-6 floors).